ISEB-PM1 · Question #196

Your project team consists of 12 people in the same building you're located in, 4 people from the West Coast office, 2 people from the Kansas City office, and 6 people from the London office. Your…

The correct answer is D. This question describes virtual teams from the Acquire Project Team process and information. See the full explanation below for the reasoning.

Resource Management

Question

Your project team consists of 12 people in the same building you're located in, 4 people from the West Coast office, 2 people from the Kansas City office, and 6 people from the London office. Your office works different hours than all the other offices. Additionally, not all of the resources in your building are available at the same times during the day. Three of the 12 team members work swing shift hours. You use tools like web conferencing and email to distribute information to the team. Which of the following is true?

Options

  • AThis question describes resource availability from the Develop Project Team process and
  • BThis question describes the staffing management plan from the Acquire Project Team process
  • CThis question describes project staff assignments from the Develop Project Team process and
  • DThis question describes virtual teams from the Acquire Project Team process and information

How the community answered

(30 responses)
  • A
    10% (3)
  • B
    3% (1)
  • C
    7% (2)
  • D
    80% (24)

Topics

#virtual teams#resource availability#staffing management#distributed teams