Resource Management
Question
Based on the network diagram in the chart, the resource working on activity G is replaced with another resource with 50 percent of the productivity of the previous resource. How long will this project take?
Options
- A44
- B51
- C52
- D36
How the community answered
(56 responses)- A9% (5)
- B5% (3)
- C70% (39)
- D16% (9)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#resource productivity#activity duration#network diagram#critical path