The correct answer is C. 52. See the full explanation below for the reasoning.

Question

Based on the network diagram in the chart, the resource working on activity G is replaced with another resource with 50 percent of the productivity of the previous resource. How long will this project take?

Options

  • A44
  • B51
  • C52
  • D36