Lessons learned are most often based upon project historical records. Lessons learned can be used to:

The correct answer is B. All of the other alternatives apply. You've hit your session limit · resets 10:20pm (America/New_York)

Organizational Aspects of Project Management

Question

Lessons learned are most often based upon project historical records. Lessons learned can be used to:

Options

  • ASee what mistakes others have made
  • BAll of the other alternatives apply
  • CSee how others have solved problems
  • DPredict trends, highlight problems and identify alternatives
  • EBoth 1) See what mistakes others have made, and 2) See how others have solved problems

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    80% (28)
  • D
    11% (4)
  • E
    6% (2)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#lessons learned#historical records#knowledge management#project closure

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice