ISEB-PM1 · Question #354
Which knowledge area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project…
The correct answer is B. Project Communications Management. Project Communications Management (B) owns the full lifecycle of project information - planning what to communicate, to whom, when, and how, then ensuring that information is generated, collected, distributed, stored, retrieved, and disposed of appropriately. This directly…
Question
Which knowledge area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?
Options
- AProject Integration Management
- BProject Communications Management
- CProject Information Management System (PIMS)
- DProject Scope Management
How the community answered
(35 responses)- A9% (3)
- B83% (29)
- C3% (1)
- D6% (2)
Explanation
Project Communications Management (B) owns the full lifecycle of project information - planning what to communicate, to whom, when, and how, then ensuring that information is generated, collected, distributed, stored, retrieved, and disposed of appropriately. This directly matches the question's wording almost verbatim, as defined in the PMBOK Guide.
Why the distractors are wrong:
- A (Integration Management) coordinates all project processes and knowledge areas together - it's the "glue," not the information pipeline itself.
- C (PIMS) is a tool/technique used within Communications Management, not a knowledge area - it's a system that stores and distributes project information.
- D (Scope Management) deals with defining and controlling what work is (and isn't) included in the project, not how information flows.
Memory tip: Think of the word "communications" literally - it's all about communicating information through its entire life (create → collect → share → store → dispose). If the question mentions the flow or handling of project information end-to-end, the answer is always Communications Management.