ISEB-PM1 · Question #369
ISEB-PM1 Question #369: Real Exam Question with Answer & Explanation
Sign in or unlock ISEB-PM1 to reveal the answer and full explanation for question #369. The question stem and answer options stay visible for context.
Question
There are seven members on the project team not counting the project manager and the sponsor. How many communication channels are there?
Options
- A21
- B28
- C36
- D42
Unlock ISEB-PM1 to see the answer