A project manager convenes a meeting to determine why the time to produce one product according to specifications has increased from one day to three days over the past month. Which tool or…
The correct answer is D. Variance analysis. ISEB ISEB-PM1 Exam
Project Control
Question
A project manager convenes a meeting to determine why the time to produce one product according to specifications has increased from one day to three days over the past month. Which tool or technique is used in this case?
Options
- AExpert judgment
- BQuality assurance
- CQuality control
- DVariance analysis
How the community answered
(33 responses)- A6% (2)
- B15% (5)
- C9% (3)
- D70% (23)
Explanation
ISEB ISEB-PM1 Exam
Topics
#variance analysis#performance measurement#quality control#schedule variance