What is one of the objectives of project risk management?

The correct answer is C. Increase the probability and impact of positive events. Project risk management aims to increase the probability and impact of positive events (opportunities) while decreasing the probability and impact of negative events (threats) - making C the correct answer. This dual focus is a core principle from the PMBOK Guide: risks aren't…

Risk Management

Question

What is one of the objectives of project risk management?

Options

  • ADecrease the probability and impact of event on project objectives.
  • BDistinguish between a project risk and a project issue so that a risk mitigation plan can be put
  • CIncrease the probability and impact of positive events.
  • DRemoval of project risk.

How the community answered

(57 responses)
  • A
    4% (2)
  • B
    11% (6)
  • C
    81% (46)
  • D
    5% (3)

Explanation

Project risk management aims to increase the probability and impact of positive events (opportunities) while decreasing the probability and impact of negative events (threats) - making C the correct answer. This dual focus is a core principle from the PMBOK Guide: risks aren't inherently bad, they include upside opportunities that a good risk management process actively tries to exploit.

Why the distractors are wrong:

  • A is only half correct - managing threats is real, but it's just one side of the objective; the full goal includes opportunities too.
  • B misrepresents the purpose - while distinguishing risks from issues is a useful practice, it's not stated as a primary objective of risk management.
  • D is incorrect because complete risk removal is generally impossible; the goal is to manage and respond to risk, not eliminate it entirely.

Memory tip: Think of project risks as a two-sided coin - threats (negative) and opportunities (positive). Risk management flips both sides in your favor: minimize threats, maximize opportunities. If an answer covers only one side, it's incomplete.

Topics

#risk management objectives#positive risks#opportunities#risk strategy