- Question #301The Project Management Lifecycle
Which of the following is involved in the initiation process group?
initiation process groupidentify stakeholdersprocess groupsproject lifecycle - Question #302The Project Management Lifecycle
Which of the following is defined by a project's life cycle and varies by application area?
product-oriented processesproject life cycleapplication areaprocess definition - Question #303Organizational Aspects of Project Management
How many knowledge areas are there according to PMBOK Guide?
PMBOK knowledge areasproject management frameworkPMI standardsproject management structure - Question #304Organizational Aspects of Project Management
Which of the following must be taken into account for every process, even if they are not explicitly listed as inputs in the process specifications?
organizational process assetsenterprise environmental factorsprocess inputsproject constraints - Question #305Quality Management
Perform quality assurance belongs to which of the following process groups?
perform quality assuranceexecuting process groupquality managementprocess groups - Question #306The Project Management Lifecycle
A project team is in which of the following processes when they finalize all activities across all of the management process groups to formally complete the project?
closing process groupproject closureproject completionprocess groups - Question #307Project Planning
Which process group defines the course of action required to attain the objectives that the project was undertaken to achieve?
planning process groupproject objectivescourse of actionprocess groups - Question #308The Project Management Lifecycle
How many process groups are there according to the PMBOK Guide?
PMBOK process groupsproject management frameworkPMI standardsfive process groups - Question #309Project Control
The Monitoring and Controlling process group contains which of the following processes?
monitoring and controllingperform quality controlprocess groupsquality management - Question #310Project Planning
Which process group establishes the total scope of a project?
planning process groupproject scopescope establishmentproject planning - Question #311The Project Management Lifecycle
Who must accept the end product for a project to be considered closed?
project closurecustomer acceptancesponsor acceptanceproject completion - Question #312Resource Management
Manage Project Team belongs to which knowledge area?
manage project teamhuman resource managementknowledge areasteam management - Question #313Project Planning
Where are product requirements and characteristics documented?
product scope descriptionproduct requirementsscope documentationrequirements artifacts - Question #314Organizational Aspects of Project Management
What are the formal and informal policies, procedures, and guidelines that could impact how the ISEB ISEB-PM1 Exam project's scope is managed?
organizational process assetsscope managementpolicies and proceduresproject constraints - Question #315The Project Management Lifecycle
Which of the following is an input to the Direct and Manage Project Execution Process?
direct and manage project executionprocess inputscorrective actionsproject integration management - Question #316Project Planning
Which of the following consists of the detailed project scope statement and its associated WBS and WBS dictionary?
scope baselineWBSscope managementproject scope statement - Question #317Project Planning
What scope definition technique is used to generate different approaches to execute and perform the work of the project?
alternatives identificationscope definitionscope techniquesrequirements - Question #318Project Planning
The scope management plan is a subsidiary of which project document?
scope management planproject management plansubsidiary plansscope planning - Question #319Resource Management
What type of project structure is a hierarchically organized depiction of the resources by type?
resource breakdown structureRBSproject structuresresource categorization - Question #320Project Control
What causes replanning of the project scope?
scope replanningapproved change requestschange managementscope control - Question #321Project Planning
Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?
WBSdeliverable-oriented decompositionhierarchical structurescope planning - Question #322Project Planning
What is a deliverable-oriented hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
WBSwork breakdown structuredeliverable-orientedproject objectives - Question #323Project Planning
What component of the project scope definition defines project exclusions?
project boundariesscope exclusionsscope definition componentsproject scope statement - Question #324Project Control
What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?
inspectionscope validationacceptance criteriadeliverables - Question #325Project Planning
Which of the following is an output of Define Scope?
Define Scopeprocess outputsproject document updatesscope management - Question #326Project Control
What is an output of Control Scope?
Control Scopework performance measurementsscope control outputsvariance - Question #327Project Planning
The decomposition technique is used to do which of the following?
decompositionWBS creationwork packagesscope planning - Question #328Communication Management
ISEB ISEB-PM1 Exam A project manager needs the project team to make a group decision. Which of the following is a method that can be used to reach a group decision?
group decision makingmajorityteam decisionsrequirements gathering - Question #329Project Planning
Decomposition is a tool and technique used in which of the following?
decompositionCreate WBSDefine Activitiesscope and schedule planning - Question #330Project Planning
Which of the following is a tool or technique of the Collect Requirements process?
Collect Requirementsgroup decision making techniquesrequirements toolsfacilitation - Question #331Project Planning
Which of the following is an input to Collect Requirements?
Collect Requirementsstakeholder registerprocess inputsrequirements management - Question #332Project Planning
The use of group creativity techniques as a tool and technique is done in which of the following processes?
group creativity techniquesCollect Requirementsrequirements elicitationfacilitation - Question #333Project Planning
Which is an input to the Collect Requirements process?
Collect Requirementsstakeholder registerprocess inputsrequirements management - Question #334Project Planning
Which of the following can be used to track the requirements throughout the project life cycle?
requirements traceability matrixrequirements trackingproject lifecyclescope management - Question #335Project Planning
Which of the following is an example of a group creativity technique?
Delphi techniquegroup creativityrequirements elicitationfacilitation techniques - Question #336Project Planning
Which process includes facilitated workshops as a tool and technique?
Collect Requirementsfacilitated workshopstools and techniquesscope planning - Question #337Project Control
Which of the following is a tool or technique used to verify scope?
Verify Scopeinspectionscope verificationtools and techniques - Question #338Project Control
Inspection is a tool and technique for which of the following processes?
Verify Scopeinspectiontools and techniquesscope management - Question #339Project Planning
What is the lowest level in the WBS at which the cost and activity durations for the work can be reliably estimated and managed?
WBSwork packagescope decompositioncost estimation - Question #340Project Planning
Many organizations categorize requirements into which of the following two categories?
requirementsproject requirementsproduct requirementsscope management - Question #341Project Planning
Plurality is a type of which of the following?
pluralitygroup decision makingCollect Requirementstools and techniques - Question #342Project Control
Which of the following events would result in a baseline update? ISEB ISEB-PM1 Exam
baseline updatechange requestscope changeproject control - Question #343Project Planning
Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?
fast trackingschedule compressionparallel activitiesschedule management - Question #344Project Planning
Which schedule development technique modifies the project schedule to account for limited resources?
critical chain methodresource constraintsschedule developmentresource optimization - Question #345Project Planning
Which schedule development tool and technique produces a theoretical early start date and late start date?
critical path methodearly start datelate start dateschedule development - Question #346Project Planning
What is the minimum a project schedule must include?
project scheduleplanned start dateplanned finish dateschedule baseline - Question #347Project Control
What cost control technique is used to compare actual project performance to planned or expected performance?
variance analysiscost controlperformance measurementearned value - Question #348Project Control
Using the following data, what is the Schedule Performance Index (SPI)? EV = $500 PV= $750 AC= $1000 BAC= $1200
Schedule Performance IndexSPIearned value managementEV calculation - Question #349Project Planning
Which enterprise environmental factors are considered during cost estimating?
cost estimatingenterprise environmental factorsmarketplace conditionscommercial databases - Question #350Resource Management
In which of the following team development stages does the team begin to work together, develop trust, and adjust to the work habits and behavior?
Tuckman modelteam developmentnorming stageteam behavior