ISEB-PM1 · Question #342
Which of the following events would result in a baseline update? ISEB ISEB-PM1 Exam
The correct answer is B. Your customer has approved a change request broadening the project scope and increasing. A baseline update (also called a re-baselining) is only warranted when an approved change request alters the original scope, schedule, or cost - option B is correct because a customer-approved scope change creates a new, formally agreed-upon target that the project should be…
Question
Which of the following events would result in a baseline update? ISEB ISEB-PM1 Exam
Options
- AYour project is behind schedule and you want your baseline to reflect estimated actual
- BYour customer has approved a change request broadening the project scope and increasing
- COne of the risks identified in the Risk Management Plan occurs resulting in a schedule delay.
- DOne of your key project team resources has left your team and no replacement is available.
How the community answered
(31 responses)- A16% (5)
- B74% (23)
- C6% (2)
- D3% (1)
Explanation
A baseline update (also called a re-baselining) is only warranted when an approved change request alters the original scope, schedule, or cost - option B is correct because a customer-approved scope change creates a new, formally agreed-upon target that the project should be measured against going forward.
Why the distractors are wrong:
- A - Being behind schedule is a performance problem, not a scope change. Updating the baseline to match actuals would hide the variance and undermine accountability; you manage the gap, not erase it.
- C - A risk occurring causes a schedule delay, but risk impacts are absorbed within the existing baseline (or handled via contingency reserves). No new agreement with the customer has been made.
- D - Losing a resource is an internal execution problem. The baseline remains intact; the team finds ways to deliver within the agreed plan or escalates through change control.
Memory tip: Think of a baseline as a contract with the customer. The only valid reason to rewrite a contract is when both parties agree to change its terms - that's exactly what an approved change request represents. If the project is simply struggling internally, the contract stays the same.