ISEB-PM1 · Question #342

Which of the following events would result in a baseline update? ISEB ISEB-PM1 Exam

The correct answer is B. Your customer has approved a change request broadening the project scope and increasing. A baseline update (also called a re-baselining) is only warranted when an approved change request alters the original scope, schedule, or cost - option B is correct because a customer-approved scope change creates a new, formally agreed-upon target that the project should be…

Project Control

Question

Which of the following events would result in a baseline update? ISEB ISEB-PM1 Exam

Options

  • AYour project is behind schedule and you want your baseline to reflect estimated actual
  • BYour customer has approved a change request broadening the project scope and increasing
  • COne of the risks identified in the Risk Management Plan occurs resulting in a schedule delay.
  • DOne of your key project team resources has left your team and no replacement is available.

How the community answered

(31 responses)
  • A
    16% (5)
  • B
    74% (23)
  • C
    6% (2)
  • D
    3% (1)

Explanation

A baseline update (also called a re-baselining) is only warranted when an approved change request alters the original scope, schedule, or cost - option B is correct because a customer-approved scope change creates a new, formally agreed-upon target that the project should be measured against going forward.

Why the distractors are wrong:

  • A - Being behind schedule is a performance problem, not a scope change. Updating the baseline to match actuals would hide the variance and undermine accountability; you manage the gap, not erase it.
  • C - A risk occurring causes a schedule delay, but risk impacts are absorbed within the existing baseline (or handled via contingency reserves). No new agreement with the customer has been made.
  • D - Losing a resource is an internal execution problem. The baseline remains intact; the team finds ways to deliver within the agreed plan or escalates through change control.

Memory tip: Think of a baseline as a contract with the customer. The only valid reason to rewrite a contract is when both parties agree to change its terms - that's exactly what an approved change request represents. If the project is simply struggling internally, the contract stays the same.

Topics

#baseline update#change request#scope change#project control