Which of the following can be used to track the requirements throughout the project life cycle?
The correct answer is A. Requirements traceability matrix. A Requirements Traceability Matrix (RTM) is purpose-built to track each requirement from its origin through design, development, testing, and delivery - giving stakeholders a clear audit trail across the entire project life cycle. The distractors each serve a different purpose…
Question
Which of the following can be used to track the requirements throughout the project life cycle?
Options
- ARequirements traceability matrix
- BScope management plan
- CProject charter
- DWork breakdown structure
How the community answered
(39 responses)- A74% (29)
- B8% (3)
- C3% (1)
- D15% (6)
Explanation
A Requirements Traceability Matrix (RTM) is purpose-built to track each requirement from its origin through design, development, testing, and delivery - giving stakeholders a clear audit trail across the entire project life cycle.
The distractors each serve a different purpose: the Scope Management Plan (B) defines how scope will be defined and controlled, not how individual requirements are tracked; the Project Charter (C) authorizes the project and identifies high-level objectives, but doesn't track detailed requirements; and the Work Breakdown Structure (D) decomposes deliverables into manageable work packages, focusing on work rather than requirements.
Memory tip: Think of the RTM as a spreadsheet where each row is a requirement and each column is a project phase - you can trace any requirement left-to-right (forward traceability) to see if it was implemented, or right-to-left (backward traceability) to see why a feature exists. If the question mentions "trace" or "track requirements," the answer is almost always the RTM.