Which of the following can be used to track the requirements throughout the project life cycle?

The correct answer is A. Requirements traceability matrix. A Requirements Traceability Matrix (RTM) is purpose-built to track each requirement from its origin through design, development, testing, and delivery - giving stakeholders a clear audit trail across the entire project life cycle. The distractors each serve a different purpose…

Project Planning

Question

Which of the following can be used to track the requirements throughout the project life cycle?

Options

  • ARequirements traceability matrix
  • BScope management plan
  • CProject charter
  • DWork breakdown structure

How the community answered

(39 responses)
  • A
    74% (29)
  • B
    8% (3)
  • C
    3% (1)
  • D
    15% (6)

Explanation

A Requirements Traceability Matrix (RTM) is purpose-built to track each requirement from its origin through design, development, testing, and delivery - giving stakeholders a clear audit trail across the entire project life cycle.

The distractors each serve a different purpose: the Scope Management Plan (B) defines how scope will be defined and controlled, not how individual requirements are tracked; the Project Charter (C) authorizes the project and identifies high-level objectives, but doesn't track detailed requirements; and the Work Breakdown Structure (D) decomposes deliverables into manageable work packages, focusing on work rather than requirements.

Memory tip: Think of the RTM as a spreadsheet where each row is a requirement and each column is a project phase - you can trace any requirement left-to-right (forward traceability) to see if it was implemented, or right-to-left (backward traceability) to see why a feature exists. If the question mentions "trace" or "track requirements," the answer is almost always the RTM.

Topics

#requirements traceability matrix#requirements tracking#project lifecycle#scope management