ISEB-PM1 · Question #336
Which process includes facilitated workshops as a tool and technique?
The correct answer is A. Collect Requirements. Collect Requirements (A) uses facilitated workshops as a key tool and technique because these sessions bring stakeholders together in a structured setting to rapidly define, reconcile, and prioritize requirements - making them highly effective for eliciting consensus and…
Question
Which process includes facilitated workshops as a tool and technique?
Options
- ACollect Requirements
- BPlan Communications
- CDevelop Project Team
- DReport Performance
How the community answered
(29 responses)- A83% (24)
- B3% (1)
- C10% (3)
- D3% (1)
Explanation
Collect Requirements (A) uses facilitated workshops as a key tool and technique because these sessions bring stakeholders together in a structured setting to rapidly define, reconcile, and prioritize requirements - making them highly effective for eliciting consensus and capturing diverse needs.
Why the others are wrong:
- Plan Communications (B) focuses on determining stakeholder communication needs and methods; its tools include communication requirements analysis and communication technology, not facilitated workshops.
- Develop Project Team (C) uses tools like training, team-building activities, and ground rules - not facilitated workshops.
- Report Performance (D) relies on variance analysis, forecasting methods, and reporting systems to communicate project status.
Memory tip: Think "workshop = requirements gathering." Facilitated workshops (like Joint Application Development sessions) are classically associated with bringing stakeholders into a room to collect what they need from the project - the word "collect" implies active, collaborative elicitation, which workshops enable perfectly.