ISEB-PM1 · Question #339
What is the lowest level in the WBS at which the cost and activity durations for the work can be reliably estimated and managed?
The correct answer is B. Work package. Work packages (B) are the lowest-level components of a WBS where cost and duration estimates become reliable - they represent discrete, assignable chunks of work with clear boundaries, making them the foundational unit for scheduling and cost control in project management. Why…
Question
What is the lowest level in the WBS at which the cost and activity durations for the work can be reliably estimated and managed?
Options
- AWork product
- BWork package
- CProject deliverable
- DScope baseline
How the community answered
(29 responses)- A3% (1)
- B79% (23)
- C10% (3)
- D7% (2)
Explanation
Work packages (B) are the lowest-level components of a WBS where cost and duration estimates become reliable - they represent discrete, assignable chunks of work with clear boundaries, making them the foundational unit for scheduling and cost control in project management.
Why the distractors fail:
- A (Work product) - a deliverable artifact, not a WBS decomposition level; it describes what is produced, not the schedulable unit of work.
- C (Project deliverable) - deliverables sit higher in the WBS hierarchy and are too broad for reliable estimation at that level.
- D (Scope baseline) - the scope baseline contains the WBS (plus the WBS dictionary and project scope statement), but is a planning document, not a WBS level.
Memory tip: Think "pack it up to ship it" - a work package is small enough to pack (estimate and assign) but meaningful enough to deliver. If you can put a person's name and a dollar sign on it, you're at the work package level.