The Monitoring and Controlling process group contains which of the following processes?
The correct answer is C. Perform Quality Control. Perform Quality Control (C) belongs to the Monitoring and Controlling process group because it involves inspecting and measuring work results against quality standards - a classic monitoring activity that checks whether outputs meet requirements. Why the distractors are wrong…
Question
The Monitoring and Controlling process group contains which of the following processes?
Options
- APlan Quality
- BPerform Quality Assurance
- CPerform Quality Control
- DIdentify Stakeholders
How the community answered
(63 responses)- A8% (5)
- B5% (3)
- C84% (53)
- D3% (2)
Explanation
Perform Quality Control (C) belongs to the Monitoring and Controlling process group because it involves inspecting and measuring work results against quality standards - a classic monitoring activity that checks whether outputs meet requirements.
Why the distractors are wrong:
- A (Plan Quality) belongs to Planning - you define quality standards before work begins, not while controlling it.
- B (Perform Quality Assurance) belongs to Executing - it audits processes to ensure standards are being followed, rather than inspecting deliverables.
- D (Identify Stakeholders) belongs to Initiating - stakeholders are identified early in the project lifecycle.
Memory tip: Think of Monitoring and Controlling as the "inspection checkpoint" - Control is the keyword that maps directly to this process group. Whenever you see "Control" or "Monitor" in a process name (Control Quality, Control Scope, Monitor Risks), it almost always lives in Monitoring and Controlling. "Plan" → Planning, "Perform QA" → Executing (you're doing something), "Identify" → Initiating.