The decomposition technique is used to do which of the following?

The correct answer is B. Subdivide project deliverables and project work into smaller, more manageable components. Decomposition is the technique of breaking down project deliverables and project work into smaller, more manageable components - ultimately producing the Work Breakdown Structure (WBS) - which is exactly what option B describes. A is wrong because subdividing estimated costs…

Project Planning

Question

The decomposition technique is used to do which of the following?

Options

  • ASubdivide the estimated costs of individual activities
  • BSubdivide project deliverables and project work into smaller, more manageable components
  • CRelate the work packages to the performing organizational units
  • DShorten the project schedule duration and the amount of resources needed

How the community answered

(40 responses)
  • A
    15% (6)
  • B
    75% (30)
  • C
    5% (2)
  • D
    5% (2)

Explanation

Decomposition is the technique of breaking down project deliverables and project work into smaller, more manageable components - ultimately producing the Work Breakdown Structure (WBS) - which is exactly what option B describes.

  • A is wrong because subdividing estimated costs describes cost budgeting or cost aggregation, not decomposition.
  • C is wrong because relating work packages to organizational units describes the Responsibility Assignment Matrix (RAM) or OBS (Organizational Breakdown Structure).
  • D is wrong because shortening schedule duration by adding resources or overlapping tasks describes crashing or fast-tracking.

Memory tip: Think of decomposition like breaking a tree into branches and leaves - you're always moving from big to small (deliverables → work packages → activities), never touching cost estimates, org charts, or schedules directly.

Topics

#decomposition#WBS creation#work packages#scope planning