ISEB-PM1 · Question #326
What is an output of Control Scope?
The correct answer is B. Work performance measurements. Work performance measurements (B) is correct because Control Scope is the process of monitoring project status and managing changes to the scope baseline - its primary output is a measurement of how scope performance is tracking against the plan (specifically, variance data…
Question
What is an output of Control Scope?
Options
- AAccepted deliverables
- BWork performance measurements
- CRequirements documentation
- DWork performance information
How the community answered
(67 responses)- A4% (3)
- B76% (51)
- C13% (9)
- D6% (4)
Explanation
Work performance measurements (B) is correct because Control Scope is the process of monitoring project status and managing changes to the scope baseline - its primary output is a measurement of how scope performance is tracking against the plan (specifically, variance data used to assess scope deviations).
Why the distractors are wrong:
- A (Accepted deliverables) is an output of Validate Scope, not Control Scope. Validate Scope is where the customer formally accepts completed deliverables.
- C (Requirements documentation) is produced during Collect Requirements and Define Scope - it's an input to later processes, not something Control Scope generates.
- D (Work performance information) is a close trap - it's the output in newer PMBOK editions (5th/6th), where raw measurements get processed into analyzed information. This question reflects older PMBOK (4th edition) terminology where the term used is specifically "measurements."
Memory tip: Think of Control Scope as the "measurement checkpoint" - you're comparing actual scope against the baseline and producing measurements of the variance. Pair it with "Validate Scope = customer acceptance (deliverables)" to keep the two scope monitoring processes distinct.