Question

What type of project structure is a hierarchically organized depiction of the resources by type?

Options

  • AOrganizational Breakdown Structure (OBS)
  • BResource Breakdown Structure (RBS)
  • CWork Breakdown Structure (WBS)
  • DProject Breakdown Structure (PBS)