Which of the following is a tool or technique of the Collect Requirements process?

The correct answer is A. Group decision making techniques. Group decision-making techniques (A) is explicitly listed as a tool and technique of the Collect Requirements process in PMBOK, used to help stakeholders evaluate and agree on requirements - methods like unanimity, majority, plurality, and dictatorship all fall under this…

Project Planning

Question

Which of the following is a tool or technique of the Collect Requirements process?

Options

  • AGroup decision making techniques
  • BProject management information system
  • CAlternative identification
  • DCommunication requirement analysis

How the community answered

(40 responses)
  • A
    73% (29)
  • B
    15% (6)
  • C
    8% (3)
  • D
    5% (2)

Explanation

Group decision-making techniques (A) is explicitly listed as a tool and technique of the Collect Requirements process in PMBOK, used to help stakeholders evaluate and agree on requirements - methods like unanimity, majority, plurality, and dictatorship all fall under this umbrella.

B (Project Management Information System) belongs to processes like Direct and Manage Project Work and Monitor and Control Project Work - it's an execution and control tool, not a requirements-gathering one. C (Alternative identification) is a tool of the Define Scope process, used to evaluate different approaches to delivering the project - it comes after requirements are collected. D (Communication requirement analysis) is a distractor that sounds plausible but isn't a recognized technique in Collect Requirements; "communications requirements analysis" belongs to Plan Communications Management.

Memory tip: Think of Collect Requirements as a people-driven process - its tools involve talking to and engaging stakeholders (interviews, workshops, focus groups, group decisions). If a tool sounds administrative (PMIS) or comes after requirements exist (alternative identification, define scope), it's likely from a different process.