Decomposition is a tool and technique used in which of the following?

The correct answer is C. Create WBS and Define Activities. Decomposition is explicitly listed as a tool and technique in both Create WBS (breaking down deliverables into smaller work packages) and Define Activities (breaking down work packages into individual schedule activities) - making C correct. A is wrong because Define Scope uses…

Project Planning

Question

Decomposition is a tool and technique used in which of the following?

Options

  • ADefine Scope and Define Activities
  • BCollect Requirements and Estimate Activity Resources
  • CCreate WBS and Define Activities
  • DCreate WBS and Estimate Activity Duration

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    84% (26)
  • D
    10% (3)

Explanation

Decomposition is explicitly listed as a tool and technique in both Create WBS (breaking down deliverables into smaller work packages) and Define Activities (breaking down work packages into individual schedule activities) - making C correct.

  • A is wrong because Define Scope uses product analysis, alternatives analysis, and expert judgment - not decomposition - and Create WBS is replaced with Define Scope.
  • B is wrong because neither Collect Requirements nor Estimate Activity Resources uses decomposition as a named tool/technique.
  • D is wrong because Estimate Activity Duration uses analogous estimating, parametric estimating, and three-point estimating - not decomposition.

Memory tip: Think of decomposition as a breaking-down tool. You break down the project scope into a WBS, then break down WBS work packages into activities - both steps use the same technique, creating a natural top-to-bottom chain: WBS → Activities = Decomposition twice.

Topics

#decomposition#Create WBS#Define Activities#scope and schedule planning