ISEB-PM1 · Question #329
Decomposition is a tool and technique used in which of the following?
The correct answer is C. Create WBS and Define Activities. Decomposition is explicitly listed as a tool and technique in both Create WBS (breaking down deliverables into smaller work packages) and Define Activities (breaking down work packages into individual schedule activities) - making C correct. A is wrong because Define Scope uses…
Question
Decomposition is a tool and technique used in which of the following?
Options
- ADefine Scope and Define Activities
- BCollect Requirements and Estimate Activity Resources
- CCreate WBS and Define Activities
- DCreate WBS and Estimate Activity Duration
How the community answered
(31 responses)- A3% (1)
- B3% (1)
- C84% (26)
- D10% (3)
Explanation
Decomposition is explicitly listed as a tool and technique in both Create WBS (breaking down deliverables into smaller work packages) and Define Activities (breaking down work packages into individual schedule activities) - making C correct.
- A is wrong because Define Scope uses product analysis, alternatives analysis, and expert judgment - not decomposition - and Create WBS is replaced with Define Scope.
- B is wrong because neither Collect Requirements nor Estimate Activity Resources uses decomposition as a named tool/technique.
- D is wrong because Estimate Activity Duration uses analogous estimating, parametric estimating, and three-point estimating - not decomposition.
Memory tip: Think of decomposition as a breaking-down tool. You break down the project scope into a WBS, then break down WBS work packages into activities - both steps use the same technique, creating a natural top-to-bottom chain: WBS → Activities = Decomposition twice.
Topics
Community Discussion
No community discussion yet for this question.