nerdexam
BCS-ISEB

ISEB-PM1 · Question #372

What are assigned risk ratings based upon?

The correct answer is B. Assessed probability and impact. Assigned risk ratings are based on assessed probability and impact (B) because a risk's severity is determined by combining how likely it is to occur with how significant its consequences would be - this two-factor evaluation is the foundation of quantitative and qualitative…

Risk Management

Question

What are assigned risk ratings based upon?

Options

  • ARoot cause analysis
  • BAssessed probability and impact
  • CExpert judgment
  • DRisk Identification

How the community answered

(40 responses)
  • A
    3% (1)
  • B
    85% (34)
  • C
    10% (4)
  • D
    3% (1)

Explanation

Assigned risk ratings are based on assessed probability and impact (B) because a risk's severity is determined by combining how likely it is to occur with how significant its consequences would be - this two-factor evaluation is the foundation of quantitative and qualitative risk analysis in frameworks like PMBOK and ISO 31000.

Why the distractors are wrong:

  • A (Root cause analysis) identifies why a risk exists, not how severe it is - it's a diagnostic tool, not a rating mechanism.
  • C (Expert judgment) may inform the assessment process but is not the basis for the rating itself; it's an input, not the formula.
  • D (Risk identification) is the earlier step of discovering risks - you must identify risks before you can rate them, but identification alone doesn't assign a rating.

Memory tip: Think of a risk rating as a simple equation - P × I = Risk Rating (Probability × Impact). If you see "rating" or "scoring" on the exam, that formula points straight to B.

Topics

#risk ratings#probability and impact#risk assessment#risk scoring

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice