ISEB-PM1 · Question #372
What are assigned risk ratings based upon?
The correct answer is B. Assessed probability and impact. Assigned risk ratings are based on assessed probability and impact (B) because a risk's severity is determined by combining how likely it is to occur with how significant its consequences would be - this two-factor evaluation is the foundation of quantitative and qualitative…
Question
What are assigned risk ratings based upon?
Options
- ARoot cause analysis
- BAssessed probability and impact
- CExpert judgment
- DRisk Identification
How the community answered
(40 responses)- A3% (1)
- B85% (34)
- C10% (4)
- D3% (1)
Explanation
Assigned risk ratings are based on assessed probability and impact (B) because a risk's severity is determined by combining how likely it is to occur with how significant its consequences would be - this two-factor evaluation is the foundation of quantitative and qualitative risk analysis in frameworks like PMBOK and ISO 31000.
Why the distractors are wrong:
- A (Root cause analysis) identifies why a risk exists, not how severe it is - it's a diagnostic tool, not a rating mechanism.
- C (Expert judgment) may inform the assessment process but is not the basis for the rating itself; it's an input, not the formula.
- D (Risk identification) is the earlier step of discovering risks - you must identify risks before you can rate them, but identification alone doesn't assign a rating.
Memory tip: Think of a risk rating as a simple equation - P × I = Risk Rating (Probability × Impact). If you see "rating" or "scoring" on the exam, that formula points straight to B.