ISEB-PM1 · Question #373
Which of the following processes includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?
The correct answer is A. Qualitative risk analysis. Qualitative risk analysis is the process of prioritizing individual risks by assessing and combining two factors: their probability of occurrence and their potential impact - making option A correct. This is typically done using a probability-impact matrix to rank which risks…
Question
Which of the following processes includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?
Options
- AQualitative risk analysis
- BQuantitative risk analysis
- CRisk management planning
- DRisk response planning
How the community answered
(44 responses)- A73% (32)
- B7% (3)
- C16% (7)
- D5% (2)
Explanation
Qualitative risk analysis is the process of prioritizing individual risks by assessing and combining two factors: their probability of occurrence and their potential impact - making option A correct. This is typically done using a probability-impact matrix to rank which risks need further attention, without assigning numerical values.
Why the distractors are wrong:
- B (Quantitative risk analysis) goes deeper, using numerical methods (like Monte Carlo simulations) to analyze the combined effect of risks on project objectives - it comes after qualitative analysis, not before.
- C (Risk management planning) is about defining how to approach and execute risk activities - it's the planning framework, not the evaluation itself.
- D (Risk response planning) is where you decide what to do about risks - developing strategies like mitigation or avoidance - which happens after you've already assessed and prioritized them.
Memory tip: Think "Qualify before Quantify." Qualitative = quick, subjective ranking (High/Medium/Low). Quantitative = deeper, numerical analysis. The question's key phrase - "assessing and combining probability and impact" - is the textbook definition of qualitative risk analysis from the PMBOK Guide.