nerdexam
BCS-ISEB

ISEB-PM1 · Question #374

Which of the following documents allows the project manager to assess risks that may require near term action?

The correct answer is C. Risk urgency assessment. Risk urgency assessment specifically evaluates which identified risks require immediate or near-term attention by considering factors like time sensitivity, symptoms, and warning signs - making it the tool a project manager uses to prioritize action timing, not just likelihood…

Risk Management

Question

Which of the following documents allows the project manager to assess risks that may require near term action?

Options

  • AProbability and impact matrix
  • BContingency analysis report
  • CRisk urgency assessment
  • DRolling wave plan

How the community answered

(54 responses)
  • A
    17% (9)
  • B
    4% (2)
  • C
    72% (39)
  • D
    7% (4)

Explanation

Risk urgency assessment specifically evaluates which identified risks require immediate or near-term attention by considering factors like time sensitivity, symptoms, and warning signs - making it the tool a project manager uses to prioritize action timing, not just likelihood or severity.

Why the distractors are wrong:

  • A. Probability and impact matrix ranks risks by how likely they are and how severe their impact would be, but says nothing about when action is needed.
  • B. Contingency analysis report (sometimes called contingency reserve analysis) deals with budget or schedule buffers for known risks - it's about resource planning, not timing of response.
  • D. Rolling wave plan is a progressive elaboration planning technique for near-term work packages, not a risk assessment tool at all.

Memory tip: Think of "urgency" literally - a risk urgency assessment answers "how soon do we need to act?" If a risk is urgent, it needs near-term action regardless of whether it's high or low probability. The word urgency = time pressure = near-term action.

Topics

#risk urgency assessment#near-term risk action#risk monitoring#risk documentation

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice