ISEB-PM1 · Question #385
Which of the following lists contain processes that are included within Project Procurement Management?
The correct answer is A. Plan purchases and acquisitions, plan contracting, request seller responses, select sellers. Option A is correct because all four processes - Plan Purchases and Acquisitions, Plan Contracting, Request Seller Responses, and Select Sellers - are legitimate processes within Project Procurement Management as defined by the PMBOK Guide (4th edition framework). Together they…
Question
Which of the following lists contain processes that are included within Project Procurement Management?
Options
- APlan purchases and acquisitions, plan contracting, request seller responses, select sellers
- BPlan purchases and acquisitions, request seller responses, select sellers, schedule control
- CPlan purchases and acquisitions, acquire project team, request seller responses, select sellers
- DPlan purchases and acquisitions, acquire project team, contract approval, select sellers
How the community answered
(16 responses)- A75% (12)
- B13% (2)
- C6% (1)
- D6% (1)
Explanation
Option A is correct because all four processes - Plan Purchases and Acquisitions, Plan Contracting, Request Seller Responses, and Select Sellers - are legitimate processes within Project Procurement Management as defined by the PMBOK Guide (4th edition framework). Together they cover the full procurement lifecycle from deciding what to buy through choosing a vendor.
Why the distractors fail:
- B includes Schedule Control, which belongs to Project Time Management, not procurement.
- C includes Acquire Project Team, which is a Project Human Resource Management process - it's about staffing your team, not buying goods or services.
- D includes both Acquire Project Team (same issue as C) and Contract Approval, which is not a named PMBOK procurement process at all.
Memory tip: Think of procurement as a shopping trip - you plan what to buy (Plan Purchases), plan how to buy it (Plan Contracting), ask sellers for quotes (Request Seller Responses), then pick a seller (Select Sellers). Any answer that sneaks in an HR process ("Acquire Project Team") or a made-up/misplaced process ("Schedule Control," "Contract Approval") is a trap.