ISEB-PM1 · Question #386
Which type of analysis is used as a general management technique within the Plan Procurements Process?
The correct answer is B. Make or buy analysis. Make-or-buy analysis (B) is a core general management technique used in the Plan Procurements process because it helps organizations decide whether to produce goods/services internally or purchase them externally - a fundamental procurement planning decision covered in the…
Question
Which type of analysis is used as a general management technique within the Plan Procurements Process?
Options
- ARisk assessment analysis
- BMake or buy analysis
- CContract value analysis
- DCost impact analysis
How the community answered
(29 responses)- A3% (1)
- B72% (21)
- C10% (3)
- D14% (4)
Explanation
Make-or-buy analysis (B) is a core general management technique used in the Plan Procurements process because it helps organizations decide whether to produce goods/services internally or purchase them externally - a fundamental procurement planning decision covered in the PMBOK Guide.
Why the distractors are wrong:
- A (Risk assessment analysis) - risk analysis is part of risk management processes, not a named technique within Plan Procurements.
- C (Contract value analysis) - this is not a recognized standard technique in the Plan Procurements process; contract types and values are outputs, not analysis tools.
- D (Cost impact analysis) - while cost is considered, "cost impact analysis" is not the specific named technique used here; it's a generic term not tied to this process.
Memory tip: Think of "Plan Procurements" as the point where you ask "Should we make it or buy it?" - that question is the analysis. The phrase "make or buy" literally names the decision you're planning around.