ISEB-PM1 · Question #389

A contract change control system defines which of the following?

The correct answer is B. Process by which the procurement can be modified. A contract change control system defines the formal process by which an approved procurement contract can be modified - covering how changes are submitted, reviewed, approved, and documented. This makes B correct: the system governs amendments to an existing contract, ensuring…

Project Control

Question

A contract change control system defines which of the following?

Options

  • AProcess by which the procurement is being satisfied
  • BProcess by which the procurement can be modified
  • CProcess by which the procurement can be obtained
  • DProcess by which the procurement can be disposed

How the community answered

(33 responses)
  • A
    15% (5)
  • B
    70% (23)
  • C
    9% (3)
  • D
    6% (2)

Explanation

A contract change control system defines the formal process by which an approved procurement contract can be modified - covering how changes are submitted, reviewed, approved, and documented. This makes B correct: the system governs amendments to an existing contract, ensuring changes go through proper channels rather than happening informally.

Why the distractors are wrong:

  • A (how procurement is satisfied) describes contract execution or performance monitoring, not a change control system.
  • C (how procurement can be obtained) describes the procurement process itself (planning, solicitation, selection) - that happens before a contract exists.
  • D (how procurement can be disposed) refers to contract closure procedures, a separate process.

Memory tip: Think of the word "control" - you only need to control something that already exists and might change. A change control system kicks in after the contract is signed, managing what happens when someone wants to alter it. If the answer involves modifying an existing agreement, it's change control.

Topics

#contract change control#procurement modification#change control system#contract administration