- Question #451Risk Management
What is the first step in preparing the risk register?
risk registerrisk identificationrisk management process - Question #452Organizational Aspects of Project Management
What is Project Portfolio Management?
project portfolio managementprogram managementorganizational grouping - Question #453The Project Management Lifecycle
When is a project finished?
project completionproject closureproject objectives - Question #454Project Planning
Define Activities and Estimate Activity Resources are processes in which project management knowledge area?
Define ActivitiesEstimate Activity Resourcestime managementscheduling - Question #455Organizational Aspects of Project Management
What characteristic do project and operational work share in common?
project vs operationsresource constraintsproject characteristics - Question #456Project Planning
What are the components of the "triple constraint"? ISEB ISEB-PM1 Exam
triple constraintscopetimecost - Question #457Organizational Aspects of Project Management
Which statement is true about the project management body of knowledge?
PMBOKproject management knowledgebody of knowledge evolution - Question #458Organizational Aspects of Project Management
What do composite organizations involve?
composite organizationorganizational structurefunctional managersproject managers - Question #459The Project Management Lifecycle
Which of the following is TRUE about most project life cycles?
project life cyclestakeholder influenceuncertaintyproject phases - Question #460Communication Management
What happens to a stakeholder's project influence over time?
stakeholder influencestakeholder managementproject lifecyclestakeholder engagement - Question #461Project Control
To which process is work performance information an input?
work performance informationcontract administrationprocess inputsmonitoring and controlling - Question #462Communication Management
Which of the following is an output of the Information Distribution Process?
information distributionprocess outputsorganizational process assetscommunication processes - Question #463The Project Management Lifecycle
Which process documents the business needs of a project and the new product, service or other result that is intended to satisfy those requirements?
project charterbusiness needsinitiationproject scope - Question #464The Project Management Lifecycle
Which process group typically consumes the bulk of a project's budget?
process groupsexecutingbudget allocationproject lifecycle - Question #465Risk Management
What process determines which risks might affect the project?
identify risksrisk identificationrisk processesrisk planning - Question #466The Project Management Lifecycle
Verification of project deliverables occurs during which process?
deliverable verificationclose projectproject closureproject phases - Question #467Project Control
Information collected on the status of project activities being performed to accomplish the project work is known as what?
work performance informationproject statusactivity monitoringdata collection - Question #468Project Control
Which is a tool used in monitoring and controlling project work?
PMISmonitoring and controllingproject toolsperformance reporting - Question #469Project Control
Which is an input to the Scope Verification Process?
scope verificationprocess inputsproject scope statementscope management - Question #470Project Control
When are deliverables accepted or not accepted? ISEB ISEB-PM1 Exam
deliverable acceptancescope verificationprocess outputsacceptance criteria - Question #471Project Control
During which process would you obtain stakeholders' formal acceptance of the completed project scope?
scope verificationformal acceptancestakeholder sign-offscope management - Question #472Project Planning
The initial development of a Project Scope Management plan uses which technique?
scope management planexpert judgmentplanning techniquesscope planning - Question #473Risk Management
What is a hierarchically organized depiction of the identified project risks arranged by risk category?
risk breakdown structurerisk categoriesrisk identificationrisk hierarchy - Question #474Project Planning
Which is a tool or technique used in scope definition?
scope definitionstakeholder analysisscope planningrequirements - Question #475Project Planning
What is the total float of the critical path?
critical pathtotal floatschedule network analysisschedule compression - Question #476Project Planning
Which of the following is the correct network diagram for the table?
network diagramactivity sequencingdependenciesschedule development - Question #477Resource Management
Which of the following is a schedule network analysis technique that takes limited resources into account?
critical chain methodresource constraintsschedule network analysisresource leveling - Question #478Project Planning
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
fast trackingschedule compressionproject riskschedule management - Question #479Project Planning
Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?
analogous estimatingcost estimationhistorical dataestimating techniques - Question #480Project Control
Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80 work-days. What should be your concern?
earned value managementcost overrunCPIschedule performance - Question #481Resource Management
Which illustrates the connection between work that needs to be done and its project team members?
responsibility matrixRACIteam assignmentsresource allocation - Question #482Resource Management
When can pre-assignment of project team members occur?
pre-assignmentteam acquisitionresource planningstaffing - Question #483Risk Management
Which process uses occurrence probability and impact on project objectives to assess the priority ISEB ISEB-PM1 Exam of identified risks?
qualitative risk analysisprobabilityimpactrisk prioritization - Question #484Risk Management
In which process might you use risk reassessment as a tool and technique?
risk monitoringrisk reassessmentrisk controltools and techniques - Question #485Project Planning
A contract management plan is a subsidiary of what other type of plan?
contract management planproject management plansubsidiary plansprocurement - Question #486The Project Management Lifecycle
Which of the following does NOT assess the value a project brings to an organization?
project valuebenefit cost analysisnet present valueneeds assessment - Question #487The Project Management Lifecycle
Your management has decided that all orders will be treated as "projects" and that project managers will be used to update orders daily, to resolve issues, and to ensure that the c...
project definitionrecurring processoperationsproject vs process - Question #488Organizational Aspects of Project Management
A project manager in a predominantly hierarchical organization has been assigned a major project with aggressive timelines. The BEST approach for developing an initial project char...
project charterhierarchical organizationstakeholder engagementinitiation - Question #489The Project Management Lifecycle
All of the following are correct statements about a project manager EXCEPT:
project manager rolecharteraccountabilitychange management - Question #490Project Planning
A new project manager is having difficulty creating a WBS with the team. To alleviate this situation, the project manager should ask for help from:
WBSproject management officeplanning supportdecomposition - Question #491Risk Management
While preparing your risk responses, you realize that you have not planned for unknown risk events. You need to make adjustments to the project to compensate for unknown risk event...
unknown risksmanagement reservecontingencyrisk response - Question #492Organizational Aspects of Project Management
You are about to begin negotiations with people from another country. Which of the following should provide guidance on what business practices are allowed and not allowed?
code of conductbusiness ethicsnegotiationsprofessional conduct - Question #493Organizational Aspects of Project Management
An employee approaches you and asks to tell you something in confidence. He advises you that he has been performing illegal activities within the company for the last year. He is f...
ethicsillegal activityprofessional conductreporting - Question #494Project Planning
What is one of the KEY objectives during contract negotiations?
contract negotiationsfair priceprocurementseller relations - Question #495Project Planning
You are a new project manager who has never managed a project before. You have been asked to plan a new project. It would be BEST in this situation to rely on _______ during planni...
historical informationplanninglessons learnednew project manager - Question #496Communication Management
If a project manager is concerned with gathering, integrating, and disseminating the outputs of all project management processes, she should concentrate on creating a better:
communications managementPMISinformation distributionproject outputs - Question #497Project Planning
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
cost budgetingcost aggregationwork packagesschedule activities - Question #498Project Control
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000
schedule performance indexearned valueSPI calculationEVM - Question #499Project Control
The project manager calculated a schedule performance index of 0.8 and a cost performance index of 1.1 for the project. What is the actual status of this project?
SPICPIearned valueproject status - Question #500Project Control
EAC (estimate at complete) is typically based on actual cost (AC) for work completed plus an ETC (estimate to complete) the remaining work. Which of the following is a valid formul...
estimate at completionEAC formulaETCearned value