ISEB-PM1 · Question #499
The project manager calculated a schedule performance index of 0.8 and a cost performance index of 1.1 for the project. What is the actual status of this project?
The correct answer is B. Behind schedule and under budget. SPI = 0.8 means the project is behind schedule - any Schedule Performance Index below 1.0 indicates less work was completed than planned. CPI = 1.1 means the project is under budget - a Cost Performance Index above 1.0 means each dollar spent is buying more than a dollar of…
Question
The project manager calculated a schedule performance index of 0.8 and a cost performance index of 1.1 for the project. What is the actual status of this project?
Options
- ABehind schedule and over budget
- BBehind schedule and under budget
- CAhead of schedule and under budget
- DAhead of schedule and over budget
How the community answered
(41 responses)- A7% (3)
- B76% (31)
- C15% (6)
- D2% (1)
Explanation
SPI = 0.8 means the project is behind schedule - any Schedule Performance Index below 1.0 indicates less work was completed than planned. CPI = 1.1 means the project is under budget - a Cost Performance Index above 1.0 means each dollar spent is buying more than a dollar of planned work.
Why the distractors are wrong:
- A is wrong because CPI = 1.1 (above 1.0) means under budget, not over.
- C is wrong because SPI = 0.8 (below 1.0) means behind schedule, not ahead.
- D is wrong on both counts - SPI < 1 is behind schedule, and CPI > 1 is under budget.
Memory tip: Think of these indices like a grade - below 1.0 is a failing grade (bad: behind schedule or over budget), above 1.0 is above average (good: ahead of schedule or under budget). The two indices are independent, so a project can score well on one and poorly on the other simultaneously.