ISEB-PM1 · Question #500
EAC (estimate at complete) is typically based on actual cost (AC) for work completed plus an ETC (estimate to complete) the remaining work. Which of the following is a valid formula for calculating…
The correct answer is A. EAC = AC + [(BAC-EV) / (Cumulative CPI * Cumulative SPI)]. Option A is correct because it follows the standard EAC formula structure - actual cost incurred (AC) plus a recalculated estimate for the remaining work - where the remaining planned value (BAC − EV) is adjusted by both cost efficiency (CPI) and schedule efficiency (SPI)…
Question
EAC (estimate at complete) is typically based on actual cost (AC) for work completed plus an ETC (estimate to complete) the remaining work. Which of the following is a valid formula for calculating EAC?
Options
- AEAC = AC + [(BAC-EV) / (Cumulative CPI * Cumulative SPI)]
- BEAC = BAC - AC
- CEAC = 1 - CPI
- DEAC = EV + [1 - (Cumulative CPI * Cumulative SPI) / BAC]
How the community answered
(48 responses)- A71% (34)
- B17% (8)
- C4% (2)
- D8% (4)
Explanation
Option A is correct because it follows the standard EAC formula structure - actual cost incurred (AC) plus a recalculated estimate for the remaining work - where the remaining planned value (BAC − EV) is adjusted by both cost efficiency (CPI) and schedule efficiency (SPI), giving a realistic forecast when a project is running behind on both dimensions.
Option B (EAC = BAC − AC) is actually a naive "spend what's left" estimate that ignores earned value entirely and doesn't account for how efficiently work has actually been done.
Option C (EAC = 1 − CPI) is dimensionally nonsensical - CPI is a dimensionless ratio, so subtracting it from 1 yields a ratio, not a currency value; it's not a recognized PM formula.
Option D rearranges valid terms but produces a nonsensical result because it divides the performance index product by BAC (mixing a ratio with a budget value) and adds it to EV, which has no basis in PMBOK methodology.
Memory tip: Think of EAC as "what you've spent + a smarter re-estimate of the rest" - the ETC portion is always (BAC − EV) divided by whatever efficiency factor you trust, and when both time and cost are off, you multiply CPI × SPI as your divisor (option A).
Topics
Community Discussion
No community discussion yet for this question.