BCS-ISEB
ISEB-PM1 · Question #500
ISEB-PM1 Question #500: Real Exam Question with Answer & Explanation
Sign in or unlock ISEB-PM1 to reveal the answer and full explanation for question #500. The question stem and answer options stay visible for context.
Question
EAC (estimate at complete) is typically based on actual cost (AC) for work completed plus an ETC (estimate to complete) the remaining work. Which of the following is a valid formula for calculating EAC?
Options
- AEAC = AC + [(BAC-EV) / (Cumulative CPI * Cumulative SPI)]
- BEAC = BAC - AC
- CEAC = 1 - CPI
- DEAC = EV + [1 - (Cumulative CPI * Cumulative SPI) / BAC]
Unlock ISEB-PM1 to see the answer
You've previewed enough free ISEB-PM1 questions. Unlock ISEB-PM1 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.