Which of the following equations is used to calculate schedule variance?

The correct answer is C. EV-PV. Schedule Variance (SV) = EV − PV, meaning you subtract what you planned to accomplish (Planned Value) from what you actually accomplished (Earned Value). A positive result means you're ahead of schedule; a negative result means you're behind. Why the distractors are wrong: A…

Project Control

Question

Which of the following equations is used to calculate schedule variance?

Options

  • AEV/PV
  • BPV/EV
  • CEV-PV
  • DPV-EV

How the community answered

(45 responses)
  • A
    2% (1)
  • B
    7% (3)
  • C
    78% (35)
  • D
    13% (6)

Explanation

Schedule Variance (SV) = EV − PV, meaning you subtract what you planned to accomplish (Planned Value) from what you actually accomplished (Earned Value). A positive result means you're ahead of schedule; a negative result means you're behind.

Why the distractors are wrong:

  • A (EV/PV) is the Schedule Performance Index (SPI) - a ratio, not a variance.
  • B (PV/EV) is simply SPI inverted; it's not a standard EVM formula at all.
  • D (PV−EV) flips the operands, giving you the opposite sign - you'd incorrectly show a positive number when behind schedule.

Memory tip: Think "Earned comes first, Planned follows" - just like progress comes before planning on a timeline. The word variance always means subtraction (not division), which eliminates A and B immediately.

Topics

#schedule variance#earned value#EV#PV