ISEB-PM1 · Question #451

What is the first step in preparing the risk register?

The correct answer is D. Risk identification. Risk identification (D) is the first step because you cannot manage risks you haven't discovered yet - the risk register is literally created during this process by documenting all potential risks, their characteristics, and their owners. Why the distractors are wrong: A…

Risk Management

Question

What is the first step in preparing the risk register?

Options

  • AQualitative risk analysis
  • BQuantitative risk analysis
  • CRisk response planning
  • DRisk identification

How the community answered

(33 responses)
  • A
    12% (4)
  • B
    6% (2)
  • C
    3% (1)
  • D
    79% (26)

Explanation

Risk identification (D) is the first step because you cannot manage risks you haven't discovered yet - the risk register is literally created during this process by documenting all potential risks, their characteristics, and their owners.

Why the distractors are wrong:

  • A (Qualitative risk analysis) comes after identification - you can only assess probability and impact once risks have been listed.
  • B (Quantitative risk analysis) is a deeper numerical analysis that follows qualitative analysis, making it even further down the process.
  • C (Risk response planning) is the last major step - you plan responses only after you've identified and analyzed risks.

Memory tip: Think of the risk management process as a funnel - you must find risks (Identify) → score them (Qualitative/Quantitative) → act on them (Response Planning). You can't score or respond to something you haven't found first. The acronym I-Q-Q-R (Identify, Qualitative, Quantitative, Response) keeps the order straight.

Topics

#risk register#risk identification#risk management process