ISEB-PM1 · Question #487

Your management has decided that all orders will be treated as "projects" and that project managers will be used to update orders daily, to resolve issues, and to ensure that the customer formally…

The correct answer is C. This is a recurring process. Option C is correct because the scenario describes recurring operations masquerading as projects - the work (processing orders, updating status, resolving issues) repeats continuously with standardized steps, which is the definition of a process, not a project. A true project…

The Project Management Lifecycle

Question

Your management has decided that all orders will be treated as "projects" and that project managers will be used to update orders daily, to resolve issues, and to ensure that the customer formally accepts the product within 30 days of completion. Revenue from the individual orders can vary from US $100 to US $150,000. The project manager will not be required to perform planning or provide documentation other than daily status. How would you define this situation?

Options

  • ABecause each individual order is a "temporary endeavor," each order is a project.
  • BThis is program management since there are multiple projects involved.
  • CThis is a recurring process.
  • DOrders incurring revenue over $100,000 would be considered projects and would involve

How the community answered

(18 responses)
  • A
    11% (2)
  • B
    6% (1)
  • C
    78% (14)
  • D
    6% (1)

Explanation

Option C is correct because the scenario describes recurring operations masquerading as projects - the work (processing orders, updating status, resolving issues) repeats continuously with standardized steps, which is the definition of a process, not a project. A true project is a temporary endeavor with a unique outcome; here, the orders are routine, repetitive business transactions dressed up with project management language.

Why the distractors fail:

  • A is wrong because calling something "temporary" isn't sufficient - projects must also produce a unique deliverable; routine orders follow the same process each time, making them operational work.
  • B is wrong because program management groups related projects to achieve strategic benefits; a stream of identical orders is not a program.
  • D is wrong (and incomplete as written) because the dollar value of work does not determine whether something is a project - a $150,000 order processed the same way as a $100 order is still a recurring process.

Memory tip: Ask yourself, "Would this work repeat in essentially the same way again next week?" If yes, it's a process (operations). If it ends and won't repeat, it's a project. Management labeling something a project doesn't make it one.

Topics

#project definition#recurring process#operations#project vs process