ISEB-PM1 · Question #488

A project manager in a predominantly hierarchical organization has been assigned a major project with aggressive timelines. The BEST approach for developing an initial project charter in this…

The correct answer is C. Create a project charter jointly with management for distribution to potential team members. In a hierarchical organization, authority and decisions flow top-down, so creating the charter jointly with management ensures it carries the necessary organizational authority and reflects the power structure's priorities - making C the best fit. Option A is wrong because…

Organizational Aspects of Project Management

Question

A project manager in a predominantly hierarchical organization has been assigned a major project with aggressive timelines. The BEST approach for developing an initial project charter in this environment is to:

Options

  • ACreate a project charter using brainstorming sessions with potential team members and
  • BCreate and present a draft project charter to potential team members and stakeholders to
  • CCreate a project charter jointly with management for distribution to potential team members
  • DCreate a project charter with the functional managers and present it to the sponsor for

How the community answered

(20 responses)
  • A
    10% (2)
  • B
    5% (1)
  • C
    80% (16)
  • D
    5% (1)

Explanation

In a hierarchical organization, authority and decisions flow top-down, so creating the charter jointly with management ensures it carries the necessary organizational authority and reflects the power structure's priorities - making C the best fit. Option A is wrong because brainstorming with potential team members contradicts hierarchical culture, where team members receive direction rather than shape foundational documents. Option B is wrong for the same reason: soliciting feedback from team members and stakeholders on a draft inverts the hierarchical dynamic and slows an already aggressive timeline. Option D is wrong because the sponsor should be a co-creator of the charter (they authorize it), not just a reviewer at the end - presenting a finished charter to the sponsor bypasses their critical role.

Memory tip: Think "match the culture." Hierarchical = top-down. The charter must be born at the top (management + sponsor), then flow down to team members. If an answer has team members shaping the charter, eliminate it in a hierarchical context.

Topics

#project charter#hierarchical organization#stakeholder engagement#initiation