Which process documents the business needs of a project and the new product, service or other result that is intended to satisfy those requirements?

The correct answer is B. Develop project charter. Develop Project Charter (B) is correct because the project charter is the initiating process that formally documents the high-level business needs, the purpose of the project, and a description of the product, service, or result the project is intended to deliver - directly…

The Project Management Lifecycle

Question

Which process documents the business needs of a project and the new product, service or other result that is intended to satisfy those requirements?

Options

  • ADevelop project management plan
  • BDevelop project charter
  • CDevelop preliminary project scope statement
  • DScope planning

How the community answered

(30 responses)
  • A
    7% (2)
  • B
    77% (23)
  • C
    13% (4)
  • D
    3% (1)

Explanation

Develop Project Charter (B) is correct because the project charter is the initiating process that formally documents the high-level business needs, the purpose of the project, and a description of the product, service, or result the project is intended to deliver - directly matching the question's definition.

  • A (Develop Project Management Plan) is wrong because the management plan defines how the project will be executed, monitored, and controlled - it's a planning process, not a needs-capture process.
  • C (Develop Preliminary Project Scope Statement) was a process in PMBOK 3rd edition but was removed in later versions; even when it existed, it was a planning process that refined scope, not the initial document capturing business needs.
  • D (Scope Planning) is a planning process focused on defining how scope will be defined, validated, and controlled - it doesn't document the original business need.

Memory tip: Think of the project charter as the project's "birth certificate" - it's the very first official document, issued at project initiation, that says why this project exists and what it's supposed to produce. If a question asks about documenting business needs or justifying a project's existence, that's always the charter.

Topics

#project charter#business needs#initiation#project scope