ISEB-PM1 · Question #462

Which of the following is an output of the Information Distribution Process?

The correct answer is E. Organizational Process Assets Updates. Organizational Process Assets Updates is the primary output of the Information Distribution process because executing this process generates project records - stakeholder notifications, meeting minutes, correspondence, lessons learned, and project reports - all of which feed…

Communication Management

Question

Which of the following is an output of the Information Distribution Process?

Options

  • AProject calendar
  • BCommunication management plan
  • CRequested changes
  • DCommunication requirement plan
  • EOrganizational Process Assets Updates

How the community answered

(45 responses)
  • A
    2% (1)
  • B
    2% (1)
  • C
    13% (6)
  • D
    4% (2)
  • E
    78% (35)

Explanation

Organizational Process Assets Updates is the primary output of the Information Distribution process because executing this process generates project records - stakeholder notifications, meeting minutes, correspondence, lessons learned, and project reports - all of which feed back into the organization's knowledge base.

Why the distractors are wrong:

  • A (Project calendar) - Produced during schedule development, not communications distribution.
  • B (Communication management plan) - This is an input to Information Distribution, not an output; it's created during Plan Communications.
  • C (Requested changes) - Not a standard output of this process; change requests stem from processes like Integrated Change Control.
  • D (Communication requirement plan) - This document doesn't exist as a standalone artifact; communication requirements are a component of the Communication Management Plan, and it's an input here anyway.

Memory tip: Think of Information Distribution as the "doing" step - you send out information, and what you get back is a richer organizational memory (updated OPAs: records, reports, lessons learned). The plan was already made; now you're documenting what actually happened.

Topics

#information distribution#process outputs#organizational process assets#communication processes