What is a hierarchically organized depiction of the identified project risks arranged by risk category?
The correct answer is B. Risk breakdown structure (RBS). Risk Breakdown Structure (RBS) is correct because it is specifically defined as a hierarchical representation of risks organized by category - it visually decomposes project risks in a tree structure, much like a Work Breakdown Structure (WBS) does for project work, making…
Question
What is a hierarchically organized depiction of the identified project risks arranged by risk category?
Options
- ARisk register
- BRisk breakdown structure (RBS)
- CRisk management plan
- DRisk category
How the community answered
(17 responses)- A6% (1)
- B71% (12)
- C6% (1)
- D18% (3)
Explanation
Risk Breakdown Structure (RBS) is correct because it is specifically defined as a hierarchical representation of risks organized by category - it visually decomposes project risks in a tree structure, much like a Work Breakdown Structure (WBS) does for project work, making patterns and concentrations of risk easy to spot.
- A (Risk Register) is wrong - it's a document that logs individual risks with details like probability, impact, and response plans, but it's a list/table, not a hierarchy organized by category.
- C (Risk Management Plan) is wrong - it describes how risk management will be conducted (processes, roles, tools), not a structured depiction of the risks themselves.
- D (Risk Category) is wrong - a risk category is simply a grouping label (e.g., "Technical," "External"), not a hierarchical depiction; it's one component within an RBS, not the structure itself.
Memory tip: Think "RBS = WBS for risks." Just as a WBS breaks work into a hierarchy, the Risk Breakdown Structure breaks risks into a hierarchy by category - same shape, different subject.