Which is a tool or technique used in scope definition?

The correct answer is C. Stakeholder analysis. ISEB ISEB-PM1 Exam

Project Planning

Question

Which is a tool or technique used in scope definition?

Options

  • ATemplates, forms and standards
  • BChange requests
  • CStakeholder analysis
  • DProject assumptions

How the community answered

(39 responses)
  • A
    8% (3)
  • B
    3% (1)
  • C
    77% (30)
  • D
    13% (5)

Explanation

ISEB ISEB-PM1 Exam

Topics

#scope definition#stakeholder analysis#scope planning#requirements