ISEB-PM1 · Question #472

The initial development of a Project Scope Management plan uses which technique?

The correct answer is C. Expert judgment. Expert judgment (C) is correct because developing a Project Scope Management plan is a planning process that relies on the knowledge and experience of individuals or groups who understand the project environment, organizational standards, and PM methodology - it's about how to…

Project Planning

Question

The initial development of a Project Scope Management plan uses which technique?

Options

  • AAlternatives identification
  • BScope decomposition
  • CExpert judgment
  • DProduct analysis

How the community answered

(48 responses)
  • A
    2% (1)
  • B
    10% (5)
  • C
    83% (40)
  • D
    4% (2)

Explanation

Expert judgment (C) is correct because developing a Project Scope Management plan is a planning process that relies on the knowledge and experience of individuals or groups who understand the project environment, organizational standards, and PM methodology - it's about how to plan, not yet what to plan.

Why the distractors are wrong:

  • A (Alternatives identification) is used in Define Scope and Collect Requirements to evaluate different approaches to meeting project objectives - it comes later.
  • B (Scope decomposition) is a technique used in Create WBS, breaking deliverables into smaller work packages - that's a later process.
  • D (Product analysis) is also used in Define Scope to translate product descriptions into deliverables - again, a later process.

Memory tip: Think of the Scope Management Plan as the "rulebook for scoping." Before you can write any rulebook, you need experts to tell you what the rules should be. Expert judgment = "ask the wise people first, before you do anything else."

Topics

#scope management plan#expert judgment#planning techniques#scope planning