ISEB-PM1 · Question #472
The initial development of a Project Scope Management plan uses which technique?
The correct answer is C. Expert judgment. Expert judgment (C) is correct because developing a Project Scope Management plan is a planning process that relies on the knowledge and experience of individuals or groups who understand the project environment, organizational standards, and PM methodology - it's about how to…
Question
The initial development of a Project Scope Management plan uses which technique?
Options
- AAlternatives identification
- BScope decomposition
- CExpert judgment
- DProduct analysis
How the community answered
(48 responses)- A2% (1)
- B10% (5)
- C83% (40)
- D4% (2)
Explanation
Expert judgment (C) is correct because developing a Project Scope Management plan is a planning process that relies on the knowledge and experience of individuals or groups who understand the project environment, organizational standards, and PM methodology - it's about how to plan, not yet what to plan.
Why the distractors are wrong:
- A (Alternatives identification) is used in Define Scope and Collect Requirements to evaluate different approaches to meeting project objectives - it comes later.
- B (Scope decomposition) is a technique used in Create WBS, breaking deliverables into smaller work packages - that's a later process.
- D (Product analysis) is also used in Define Scope to translate product descriptions into deliverables - again, a later process.
Memory tip: Think of the Scope Management Plan as the "rulebook for scoping." Before you can write any rulebook, you need experts to tell you what the rules should be. Expert judgment = "ask the wise people first, before you do anything else."