ISEB-PM1 · Question #471
During which process would you obtain stakeholders' formal acceptance of the completed project scope?
The correct answer is B. Scope verification. Scope Verification is the process specifically designed to obtain formal acceptance of completed deliverables from stakeholders - it's the official sign-off step where customers or sponsors confirm the work matches what was agreed upon. Why the distractors are wrong: A (Quality…
Question
During which process would you obtain stakeholders' formal acceptance of the completed project scope?
Options
- AQuality control
- BScope verification
- CScope control
- DClose project
How the community answered
(28 responses)- A4% (1)
- B71% (20)
- C14% (4)
- D11% (3)
Explanation
Scope Verification is the process specifically designed to obtain formal acceptance of completed deliverables from stakeholders - it's the official sign-off step where customers or sponsors confirm the work matches what was agreed upon.
Why the distractors are wrong:
- A (Quality Control) focuses on inspecting deliverables for defects and ensuring they meet quality standards - it's about correctness, not acceptance.
- C (Scope Control) manages changes to the project scope baseline going forward - it's reactive and ongoing, not a sign-off process.
- D (Close Project) finalizes all administrative activities and archives project documents - acceptance of scope should already be done before closing the project.
Memory tip: Think of Scope Verification as "Verified = Sign Here." The "V" in Verification = validated by the customer's signature. It comes before Close Project, so imagine a checklist: verify scope → get signature → then close.