ISEB-PM1 · Question #457
Which statement is true about the project management body of knowledge?
The correct answer is B. Constantly evolving. Option B is correct because the Project Management Body of Knowledge (PMBOK) is a living, dynamic collection of knowledge - it is periodically updated (the PMBOK Guide is now in its 7th edition) as the profession evolves, new practices emerge, and the field matures. Why the…
Question
Which statement is true about the project management body of knowledge?
Options
- ARecognized by every project manager
- BConstantly evolving
- CThe sum of all knowledge related to project management
- DA sum of knowledge that should be applied on every project
How the community answered
(41 responses)- A12% (5)
- B80% (33)
- C2% (1)
- D5% (2)
Explanation
Option B is correct because the Project Management Body of Knowledge (PMBOK) is a living, dynamic collection of knowledge - it is periodically updated (the PMBOK Guide is now in its 7th edition) as the profession evolves, new practices emerge, and the field matures.
Why the distractors are wrong:
- A is incorrect because not every project manager recognizes or applies the PMBOK; awareness and adoption vary widely across industries and regions.
- C is a close trap - the PMBOK is not the sum of all knowledge in project management. It represents the subset that is widely recognized as good practice, not every technique or method ever used.
- D is incorrect because the PMBOK explicitly states that not all knowledge, skills, or practices need to be applied uniformly on every project - good judgment is required to select what's appropriate for each context.
Memory tip: Think of the PMBOK like a living textbook that gets revised editions - it's never "finished" and always evolving with the profession. If an answer choice says PMBOK is complete, universal, or mandatory, it's wrong.
Topics
Community Discussion
No community discussion yet for this question.