Question
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
Options
- AThe risk of achieving the shortened project time is increased.
- BThe critical path will have positive total float.
- CContingency reserves are released for redeployment by the project manager.
- DDuration buffers are added to maintain a focus on planned activity durations.