ISEB-PM1 · Question #485
A contract management plan is a subsidiary of what other type of plan?
The correct answer is B. Project management plan. A contract management plan is a subsidiary plan nested within the Project Management Plan (option B), which serves as the master document that integrates and coordinates all subsidiary plans - including procurement, risk, schedule, cost, and scope - into a cohesive whole. Why…
Question
A contract management plan is a subsidiary of what other type of plan?
Options
- AResource plan
- BProject management plan
- CCost control plan
- DExpected monetary value plan
How the community answered
(63 responses)- A16% (10)
- B70% (44)
- C5% (3)
- D10% (6)
Explanation
A contract management plan is a subsidiary plan nested within the Project Management Plan (option B), which serves as the master document that integrates and coordinates all subsidiary plans - including procurement, risk, schedule, cost, and scope - into a cohesive whole.
Why the distractors are wrong:
- A (Resource plan): The resource management plan is itself another subsidiary of the project management plan, not a parent to the contract management plan.
- C (Cost control plan): Cost control is a process/technique, not a plan document that contains other plans.
- D (Expected monetary value plan): EMV is a risk analysis calculation method (probability × impact), not a plan type at all.
Memory tip: Think of the Project Management Plan as a "binder of binders" - it holds all subsidiary plans (contract, risk, schedule, cost, quality, etc.) as chapters. If a question asks what contains any subsidiary plan, the answer is almost always the Project Management Plan.