Information collected on the status of project activities being performed to accomplish the project work is known as what?

The correct answer is B. Work performance information. Work performance data is the raw information collected during project execution (e.g., percent complete, start/finish dates, costs incurred). Once analyzed and contextualized, it becomes Work Performance Information (B) - the processed, meaningful status of project activities…

Project Control

Question

Information collected on the status of project activities being performed to accomplish the project work is known as what?

Options

  • AProject management information system
  • BWork performance information
  • CWork breakdown structure
  • DVariance analysis

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    76% (16)
  • C
    14% (3)
  • D
    5% (1)

Explanation

Work performance data is the raw information collected during project execution (e.g., percent complete, start/finish dates, costs incurred). Once analyzed and contextualized, it becomes Work Performance Information (B) - the processed, meaningful status of project activities that tells you how the work is actually going against the plan.

  • A (PMIS) is wrong because a PMIS is the system/tool used to collect, store, and distribute project data - it's the container, not the content.
  • C (WBS) is wrong because a Work Breakdown Structure is a planning artifact that decomposes deliverables into work packages - it doesn't report status.
  • D (Variance Analysis) is wrong because that's a specific technique used to compare planned vs. actual performance - it's a method of analysis, not the information itself.

Memory tip: Think of it as a pipeline - raw facts collected = Work Performance Data, those facts processed into meaningful status = Work Performance Information, and that information packaged into reports = Work Performance Reports. The question asks for the status of activities being performed, which is the middle stage: Information.