ISEB-PM1 · Question #481
Which illustrates the connection between work that needs to be done and its project team members?
The correct answer is D. Responsibility matrix. A Responsibility Matrix (also called a RACI chart or RAM - Responsibility Assignment Matrix) directly maps project work to team members, showing who is Responsible, Accountable, Consulted, and Informed for each task - making it the explicit link between work and people. A Work…
Question
Which illustrates the connection between work that needs to be done and its project team members?
Options
- AWork breakdown structure
- BNetwork diagrams
- CStaffing management plan
- DResponsibility matrix
How the community answered
(39 responses)- A3% (1)
- B15% (6)
- C8% (3)
- D74% (29)
Explanation
A Responsibility Matrix (also called a RACI chart or RAM - Responsibility Assignment Matrix) directly maps project work to team members, showing who is Responsible, Accountable, Consulted, and Informed for each task - making it the explicit link between work and people. A Work Breakdown Structure (A) breaks down deliverables into manageable components but doesn't assign people to them. Network diagrams (B) show task sequencing and dependencies, not team assignments. A Staffing Management Plan (C) describes how roles will be acquired and managed over time, but doesn't map specific work items to specific individuals.
Memory tip: Think of the word "responsibility" - it contains both the work (what you're responsible for) and the person (who bears that responsibility), making the Responsibility Matrix the natural bridge between the two.