ISEB-PM1 · Question #490
A new project manager is having difficulty creating a WBS with the team. To alleviate this situation, the project manager should ask for help from:
The correct answer is C. The project management office. The Project Management Office (PMO) exists precisely to support project managers with methodology, templates, standards, and guidance - including WBS development. When a PM lacks experience with a technique, the PMO is the institutional resource that provides structured…
Question
A new project manager is having difficulty creating a WBS with the team. To alleviate this situation, the project manager should ask for help from:
Options
- AThe sponsor.
- BOther project managers.
- CThe project management office.
- DThe team.
How the community answered
(34 responses)- A18% (6)
- B3% (1)
- C71% (24)
- D9% (3)
Explanation
The Project Management Office (PMO) exists precisely to support project managers with methodology, templates, standards, and guidance - including WBS development. When a PM lacks experience with a technique, the PMO is the institutional resource that provides structured, process-level help.
Why the distractors are wrong:
- (A) The sponsor funds and champions the project but is not responsible for project management methodology or technique guidance.
- (B) Other project managers could informally help, but this is ad hoc and not the formally designated support structure - the exam favors the correct organizational answer.
- (D) The team already has the PM struggling to work with them; the problem isn't team participation, it's the PM's lack of WBS expertise.
Memory tip: Think of the PMO as the "PM's manager" for process questions. Any time an exam question involves a PM needing methodology support, templates, training, or standards - the PMO is almost always the answer. The sponsor gives authority, the team does the work, but the PMO provides the how.
Topics
Community Discussion
No community discussion yet for this question.