ISEB-PM1 · Question #465

What process determines which risks might affect the project?

The correct answer is B. Identify Risks. Identify Risks (B) is the process specifically designed to determine which risks might affect the project - it involves systematically finding, recognizing, and documenting potential risk events and their characteristics. Why the distractors are wrong: A (Qualitative Risk…

Risk Management

Question

What process determines which risks might affect the project?

Options

  • AQualitative risk analysis
  • BIdentify Risks
  • CPlan Risk Management
  • DQuantitative risk analysis

How the community answered

(64 responses)
  • A
    3% (2)
  • B
    81% (52)
  • C
    9% (6)
  • D
    6% (4)

Explanation

Identify Risks (B) is the process specifically designed to determine which risks might affect the project - it involves systematically finding, recognizing, and documenting potential risk events and their characteristics.

Why the distractors are wrong:

  • A (Qualitative Risk Analysis) comes after risks are identified; it prioritizes already-known risks by assessing their probability and impact.
  • C (Plan Risk Management) defines how risk activities will be conducted (roles, methodology, timing) - it's the planning framework, not the discovery process.
  • D (Quantitative Risk Analysis) numerically analyzes the effect of identified risks on project objectives - again, risks must already be known before this step.

Memory tip: Think of the process order as a pipeline - you can't analyze or plan responses to risks you haven't found yet. "Identify" literally means "find them first," so Identify Risks always precedes any analysis process.

Topics

#identify risks#risk identification#risk processes#risk planning