What is one of the KEY objectives during contract negotiations?

The correct answer is A. Obtain a fair and reasonable price. Obtaining a fair and reasonable price (A) is a foundational objective in contract negotiations because the goal is a mutually beneficial agreement - one that is equitable to both buyer and seller, ensuring the seller can perform while the buyer receives value. Option B is wrong…

Project Planning

Question

What is one of the KEY objectives during contract negotiations?

Options

  • AObtain a fair and reasonable price.
  • BNegotiate a price under the seller's estimate.
  • CEnsure that all project risks are thoroughly delineated.
  • DEnsure that an effective communications management plan is established.

How the community answered

(51 responses)
  • A
    78% (40)
  • B
    2% (1)
  • C
    12% (6)
  • D
    8% (4)

Explanation

Obtaining a fair and reasonable price (A) is a foundational objective in contract negotiations because the goal is a mutually beneficial agreement - one that is equitable to both buyer and seller, ensuring the seller can perform while the buyer receives value. Option B is wrong because deliberately negotiating below the seller's estimate can undermine the seller's ability to deliver, leading to cut corners or disputes - "winning" on price at the seller's expense is not a sound contracting principle. Option C is a project risk management activity, not a core negotiation objective; risks are managed throughout the project, not "solved" at contract signing. Option D belongs to communications planning, a separate knowledge area entirely unrelated to procurement negotiations.

Memory tip: Think of contract negotiation as a handshake, not a fight - both parties must walk away able to hold up their end. "Fair and reasonable" is the standard phrase used in procurement (especially in government/federal contracting), so when you see it on an exam, it's almost always correct in this context.