PK0-004 Exam Questions
1,066 real PK0-004 exam questions with expert-verified answers and explanations. Page 18 of 22.
- Question #851Tools and documentation
The AC plus ETC is known as:
earned value managementEACEVM formulascost performance - Question #852Project life cycle phases
Agate review also is considered:
gate reviewphase gateproject auditlifecycle checkpoint - Question #853Project life cycle phases
A project manager is working on a large, complex project. While creating the project schedule, the project manager defines key points at which progress to date can be identified. W...
milestone developmentproject scheduleschedule managementprogress tracking - Question #854Project management concepts
A new project manager was hired to help transition projects from the waterfall style to an approach based on iterative refinement. This method has never been used by the organizati...
PMOAgile transformationmethodology governanceorganizational change - Question #855Project management concepts
Joe. a project team member, has had excessive absences and poor work performance. The project manager has spoken with Joe and his manager multiple times with no success. Joe's nega...
team performanceconflict resolutionhuman resourcesteam management - Question #856Project management concepts
A project with a fixed budget is behind schedule. Immediately after the project due date, resources are allocated to other high-priority projects. Which of the following should the...
fixed budgetresource constraintsschedule recoveryvendor management - Question #857Tools and documentation
During the planning phase, a scheduler uses a WBS as a reference to create a list of activities. The next step of the process is to provide a sequence for all the activities. With...
network diagramactivity sequencingWBSschedule development - Question #858Project management concepts
A vendor specifies several enhancement options in a project's SOW. The project manager receives approval for a budget increase to proceed with the enhancements. Which of the follow...
change managementSOWchange control processbudget change - Question #859Project management concepts
A project manager holds weekly project status meetings with the project team and an outside contractor. One of the team members is best friends with the contractor, so discussions...
meeting managementcommunication planteam dynamicsstakeholder engagement - Question #860Basics of IT and governance
Which of the following is an example of quantitative risk management?
quantitative riskannual loss expectancyrisk analysisrisk management - Question #861Project management concepts
Joe, a highly skilled consultant, has threatened to quit on several occasions. Although Joe is difficult to work with, he has the skills required to complete a critical project for...
resource managementrisk mitigationknowledge transferteam dynamics - Question #862Tools and documentation
Task A has a duration of 2 days and is a predecessor of task B, which has a duration of 3 days and is a predecessor of task C. Task C has a duration of 4 days. Task D has a start-t...
lag timetask dependenciescritical pathschedule calculation - Question #863Tools and documentation
A program manager asks for a visual representation of tasks, including the start and end dates. Which of the following tools should the project manager provide?
Gantt chartvisual schedulingproject timelineplanning tools - Question #864Tools and documentation
A PM is interested in outsourcing a project deliverable but is uncertain of the company's offerings. Which of the following documents would be most appropriate for the PM to send t...
procurement documentsSOWvendor managementoutsourcing - Question #865Basics of IT and governance
Which of the following would MOST likely trigger a business continuity response?
business continuitydisaster recoveryIT infrastructuredata center - Question #866Tools and documentation
A project stakeholder is disappointed the team was not included in some key decisions. This resulted in extra discussions and rework. Which of the following documents should the pr...
RACI chartstakeholder managementroles and responsibilitiesdecision authority - Question #867Project management concepts
To resolve a dispute between two project team members, the project manager allows both parties to provide input on the final design. Which of the following resolution techniques is...
conflict resolutioncompromisingteam dynamicsnegotiation techniques - Question #868Tools and documentation
During the quality review of a change request, a required feature is discovered to be missing from the build. The documentation the developer received does not mention the feature;...
version controlchange managementdocumentation managementquality control - Question #869Project life cycle phases
Two team members are discussing the lessons learned from the last testing release. Many quality defects were not reported, and the progress report is not accurate. Which of the fol...
lessons learnedclosing phasequality defectsperformance reporting - Question #870Project management concepts
A company is excited about a project and wishes to generate external enthusiasm for the ensuing product. Which of the following methods would BEST help achieve this goal?
project kickoffexternal communicationsstakeholder engagementpublicity - Question #871Project management concepts
Halfway through a project, the project manager is told it needs to be completed four weeks earlier than originally planned. Which of the following will MOST likely be impacted to a...
triple constraintschedule compressionbudget impactresource management - Question #872Project management concepts
Joe, a team member, is dissatisfied with his assigned project tasks, and he communicates this to his manager. His manager arranges a meeting with the project manager. Together, the...
organizational structurematrix organizationfunctional managementresource authority - Question #873Tools and documentation
In the postmortem analysis of a project filled with scope creep, the project manager would like to reference what was initially agreed upon and promised to the customer as delivera...
statement of workscope managementscope creepdeliverables baseline - Question #874Tools and documentation
A project team is measured each quarter on KPIs, such as burn rate, earned value, and delivery time. Which of the following can be used to display this information?
status reportKPIsearned valueperformance metrics - Question #875Project life cycle phases
A project team is ready to start working on a project; however, the project manager says the work needs to be planned first. Which of the following is MOST likely to be produced du...
planning phaseGantt chartproject scheduleplanning workshop - Question #876Tools and documentation
A project manager is determining the strategy and response for each risk. Which of the following would BEST allow the project manager to complete the register? (Choose two.)
risk registerprobabilityimpactrisk assessment - Question #877Tools and documentation
A project team just updated several risk response strategies in the risk management plan. Which of the following documents should be updated NEXT?
risk management plandocument controlproject management planrisk response - Question #878Tools and documentation
An anticipated risk event occurred, and the project risk register was updated. Which of the following is the NEXT document that needs to be updated?
issue logrisk eventrisk registermonitoring and control - Question #879Project management concepts
After a change request is approved, a vendor shares the estimated delivery date with project management. A key stakeholder requests to have this change completed by an earlier date...
vendor negotiationschedule managementstakeholder requestschange management - Question #880Project life cycle phases
A project sponsor requests an urgent change to the project scope that positively impacts the performance of the end product. Which of the following should the project manager do FI...
change managementscope changechange control processsponsor authority - Question #881Project management concepts
A project team has identified project risks. Which of the following is the NEXT step?
risk managementrisk process stepsrisk communication - Question #882Project life cycle phases
During the scoping of a new project, external risks are being evaluated. Which of the following must be reviewed in addition to scope, budget, and schedule?
project scopingproject constraintsrequirementsrisk evaluation - Question #883Project management concepts
A manufacturer won a contract to build medical equipment, which represents an extension of its main computer assembling business. Considering the standards between each line of bus...
quality constraintsregulatory standardsproject constraintscompliance - Question #884Project life cycle phases
At the conclusion of a project, the sponsor wants to review the performance of the project with a postmortem financial review. Which of the following are included in the review? (C...
earned value managementproject closurefinancial reviewcost management - Question #885Tools and documentation
A project manager is working with the legal department on a document that details the terms of the procurement with one of the vendors. This document is known as a:
procurementcontractvendor managementlegal documents - Question #886Project management concepts
The project manager for a multinational project is evaluating the option of scheduling face-to-face meetings during the release of a new system. The goal is to provide 24/7 coverag...
risk mitigationmultinational projectsrisk strategiescommunication planning - Question #887Project management concepts
A project manager sends a scheduled project newsletter to all employees of the organization. Which of the following represents the communication method the project manager used?
push communicationcommunication methodsproject newsletter - Question #888Tools and documentation
A project's purpose must be documented so the project manager can ensure the project stays within the parameters of what the client wants. Which of the following BEST covers this i...
scope statementproject documentationscope management - Question #889Project management concepts
New funding was released for a project. Which of the following roles is MOST likely responsible for reviewing and updating the budget?
project manager rolebudget managementproject rolesfunding - Question #890Basics of IT and governance
Which of the following activities should be done by a resource other than the PMO?
PMO responsibilitiesproject charterorganizational governanceproject manager roles - Question #891Project management concepts
A project in development has excessive power requirements. In response, the company is going to use solar and wind power. Which of the following risk strategies is being utilized?
risk mitigationrisk strategiesenvironmental constraints - Question #892Tools and documentation
To facilitate product testing, an outside vendor was contracted to provide resources for project completion. Each resource will be given network and door access. The outside vendor...
NDAvendor managementprocurement documentsresource onboarding - Question #893Basics of IT and governance
A manufacturer decides to shift the management of a specific product line to a different department. Which of the following changes is taking place?
reorganizationorganizational changebusiness drivers - Question #894Basics of IT and governance
A highly experienced resource, who is working in the network security department, needs to be allocated to a project. The project manager wants to negotiate the terms of participat...
functional organizationorganizational structurePM authorityresource management - Question #895Project management concepts
In a functional organization, a project team member is known to be late on deliverables and regularly delays projects. A better resource is available but is not assigned to work on...
negotiationresource managementfunctional organizationresource allocation - Question #896Project management concepts
A remote resource on a building project does not have reliable telecommunications. Which of the following is the BEST way to communicate with the resource prior to the start of exe...
communication methodsremote resourcesface-to-face communication - Question #897Project life cycle phases
Since the CCB authorized proceeding with a formal change request, the project manager and team have been working to implement the change into production. Which of the following act...
change managementCCBchange control processcommunication - Question #898Project life cycle phases
Which of the following project phases would include a feasibility study?
feasibility studyinitiating phaseproject phases - Question #899Project management concepts
A regulatory project is behind schedule, and the project manager informs the steering committee that more resources are needed to complete the automation requirements on time. Howe...
risk mitigationworkaroundschedule managementregulatory compliance - Question #900Basics of IT and governance
In which of the following organizational types would the project manager have little or no authority over the project's personnel resources?
functional organizationPM authorityorganizational structureresource control