PK0-004 · Question #880

PK0-004 Question #880: Real Exam Question with Answer & Explanation

The correct answer is D: Notify the project team to prioritize the change.. When a project sponsor - the highest authority on a project - requests an urgent, beneficial scope change, the project manager should first notify the project team to prioritize the work.

Question

A project sponsor requests an urgent change to the project scope that positively impacts the performance of the end product. Which of the following should the project manager do FIRST?

Options

  • AAsk the stakeholder to submit a change request.
  • BDocument the change and notify the stakeholders.
  • CChange the project schedule with new estimates.
  • DNotify the project team to prioritize the change.

Explanation

When a project sponsor - the highest authority on a project - requests an urgent, beneficial scope change, the project manager should first notify the project team to prioritize the work.

Common mistakes.

  • A. Asking the sponsor to submit a formal change request delays action when the authorizing executive has already communicated the change; formal documentation follows team mobilization in an urgent scenario.
  • B. Documenting the change and notifying stakeholders is a necessary step but occurs after the team has been directed to act on the sponsor's urgent request.
  • C. Updating the project schedule with new estimates requires team input first; revising the schedule cannot be the first action before the team has assessed the work involved.

Concept tested. Project manager response to urgent sponsor-initiated scope change

Community Discussion

No community discussion yet for this question.