CompTIA
PK0-004 · Question #879
PK0-004 Question #879: Real Exam Question with Answer & Explanation
Sign in or unlock PK0-004 to reveal the answer and full explanation for question #879. The question stem and answer options stay visible for context.
Question
After a change request is approved, a vendor shares the estimated delivery date with project management. A key stakeholder requests to have this change completed by an earlier date. Which of the following is the BEST action for the project manager to take?
Options
- ANegotiate with the vendor to complete the change earlier.
- BEvaluate the impact of switching tasks on the schedule.
- CConsult with the CCB about the request.
- DConfront the stakeholder about the unrealistic request.
Unlock PK0-004 to see the answer
You've previewed enough free PK0-004 questions. Unlock PK0-004 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.