An anticipated risk event occurred, and the project risk register was updated. Which of the following is the NEXT document that needs to be updated?

The correct answer is A. Issue log. The risk has become an issue now. Therefore, the issue log should be updated.

Tools and documentation

Question

An anticipated risk event occurred, and the project risk register was updated. Which of the following is the NEXT document that needs to be updated?

Options

  • AIssue log
  • BMitigation plan
  • CMilestone list
  • DProject plan

How the community answered

(34 responses)
  • A
    85% (29)
  • B
    3% (1)
  • C
    3% (1)
  • D
    9% (3)

Explanation

The risk has become an issue now. Therefore, the issue log should be updated.

Topics

#issue log#risk event#risk register#monitoring and control