A project team just updated several risk response strategies in the risk management plan. Which of the following documents should be updated NEXT?

The correct answer is A. Management plan. When risk response strategies are updated in the risk management plan, the overarching project management plan must be updated next to keep all subsidiary plans aligned.

Tools and documentation

Question

A project team just updated several risk response strategies in the risk management plan. Which of the following documents should be updated NEXT?

Options

  • AManagement plan
  • BScope statement
  • CIssue log
  • DCommunication plan

How the community answered

(31 responses)
  • A
    74% (23)
  • B
    13% (4)
  • C
    10% (3)
  • D
    3% (1)

Why each option

When risk response strategies are updated in the risk management plan, the overarching project management plan must be updated next to keep all subsidiary plans aligned.

AManagement planCorrect

The project management plan is the master document that integrates all subsidiary plans, including the risk management plan; any change to a subsidiary plan - such as updated risk response strategies - must be reflected in the management plan to maintain consistency and serve as the authoritative project baseline.

BScope statement

The scope statement defines project deliverables and boundaries; changes to risk response strategies do not alter the project scope.

CIssue log

The issue log tracks problems that have already occurred, not planned risk responses or future risk strategies.

DCommunication plan

The communication plan governs how and when information is distributed; updating risk strategies does not change communication channels or cadence.

Concept tested: Project management plan updates reflecting risk strategy changes

Topics

#risk management plan#document control#project management plan#risk response